SAP APO Interview questions below are some SAP APO Interview Questions & Answers for Experienced & Freshers, you are at right place. There are a lot of possibilities for many reputed organizations in the world. According to analysis SAP, APO has a market share of about 1.6%. So, You still have the opportunity to move to progress in your career in SAP APO. Vintage IT Solutions offers advanced SAP APO Interview Questions 2018 that helps you in cracking your interview & acquire dream career as SAP APO Developer.SAP APO Interview Questions & Answers |
SAP APO Interview Questions & Answers
Q. How can a Planning version be frozen and unfrozen?
A. Planning Version can be frozen and unfrozen doing Function Module /SAPAPO/TS_PAREA_VERSIO_FREEZE so that no further changes to the planning version can be done.
Q. What is Release Profile?
A. Release Profile is used to publish time series data from DP to SNP/PPDS. You must define the DP Planning Area and time series key figure the data in which is released and the SNP Category Type (typically FA) to which data is released. You may have a Daily Buckets Profile it will define the number of working days starting on and from the From Date if released online/ interactively or that many workdays of the planning horizon when the release is moved out in the background. The Period Split (blank, 1 and 2) field in the SNP2 tab of location-product master determines how demand plan is released to SNP from DP (how bucketed data is disaggregated to the workdays).
Q. What is the method of Period Factor?
A. Period Factor managed in the SNP PPM or Transportation Lane determines the Availability Date of a Receipt element within a time bucket (period). The system determines the specific availability date/time of the receipt components within a period, by adding a time period to the start time of the period. You can enter a factor between 0 and 1, where 0 is the start of the period, 0.5 the middle, and 1 the end of the period. When determining the availability date/time, the system needs into consideration all weekdays, meaning that it does not take into consideration any days that have been determined as non-workdays in the calendars.
Period Factor used is .71 = 7×0.71 = 4.97 or 5 days from optimizer of weekly bucket resulting in a Friday.
If Period Factor is not managed in PPM or Transportation Lane then the User Period Factor indicator and the Period Factor value maintained in the Lot Size tab of the location-product combination is used. If this is not maintained a default value of 0.5 is used.
Q. What determines stock sections presented in Stock on Hand key figure?
A. The categories described in Category Group ST1 (can be maintained in table /SAPAPO/APOCGC) manage the stock categories that are presented in the Original bucket in the Stock on Hand key figure. Subsequent buckets are dynamically computed.
Q. Does dynamic signals give up in Alert Monitor?
A.Dynamic Signals do not show up in the stand-alone alert monitor. Network alerts are to show pegging relations.